Pandemic's 2nd wave affects momentum of road construction, but unlikely to materially change trend: Crisil
As many as 45-50% of under-construction projects that were awarded between fiscals 2016 and 2018 are delayed by 8-9 months on average, beyond their scheduled completion date (SCOD), largely because of de- scoping/delinking, and financing issues pertaining to a few developers.A large chunk 66% of the projects awarded over fiscals 2019-2021 - are yet to commence construction awaiting financial closures and appointed dates. The under-construction projects face labour issues following the pandemic. The government's steps to extend milestones and SCODs ranging from 3-6 months provides them with the needed cushion.